This deal was sourced on market, secured with combo of private and hard money, then resold on the market.
We started this project with a Stop Work from the city because we removed a tree without the proper permit. (OOPS!) After completing the necessary paperwork, we were able to get back to work. This put us 2 weeks behind right from the beginning.
Cold, shorter days result in a slower work pace for laborers. They have to be more careful / slower in the rain and dark, more call outs due to sickness, longer set up / take down each day with heaters and lighting, all these factors added together result in another 2-3 weeks added to our estimate.
High end finishes are much different. Every detail matters and everything costs more! We knew this, but did not calculate correctly, our estimates were too low.
This property lacked solid comparable sales from the beginning. We estimated what the view was worth ($~50k) to justify our ARV, which was used against us by the Selling Agent on the back end.
Sagareus Real Estate is delighted to be highlighted in the Top 20 Picks for Property Management Companies in Bellevue, WA by PropertyManagement.com in...